GHENT BRIDGE WATER MAIN REPLACEMENT

Request email notification when page changes E-Notify
Project Description

The 6-inch water main under the Ghent Ave. bridge in Kettering is being replaced with an 8-inch water main during the city’s bridge reconstruction project. The project will start in September, during which time the bridge will go out of service.

Contractor: Strum

Status: The project began in September 2017 and was completed in December 2017.

Bid Results: TBA

Project Manager: Ed Schlaack
Email: SchlaackE@mcohio.org