BROMFIELD WATER MAIN REPLACEMENT

Request email notification when page changes E-Notify
Project Description

Montgomery County Environmental Services (MCES) is replacing 6" water mains on North and South Bromfield Rd. between Far Hills Ave. and Shroyer Rd. with larger 8” water mains.  MCES is also replacing a 10” line on Shroyer Rd. with a 12” line that has been installed using horizontal directional drilling. The project will eliminate a couple of small lines that run behind the homes in an easement, and install a new water main on Storms Rd. to serve residents.  The water work in completed and Kettering will repave the area streets in 2018.

Contractor: Ford Development

Status: The project began in March 2017 and is expected to finish in June 2018.

Bid Results:
Bid Tab

Project Manager: Ed Schlaack / David Swanson
Email: SchlaackE@mcohio.org / SwansonD@mcohio.org

BROMFIELD   Vicinity Map